POwEr SAvE LEvELS
In grid-interactive models, the power save levels affect the selling and charging functions. The master
inverter is set at the lowes power save level, which means it always acts first. The slaves should be set
at higher levels, causing them to assist the master as necessary when selling power or charging.
ADV/FX/STACK------------P01
(ANY SCREEN IN STACK PHASE)
DOWN INC DEC
ADV/FX/STACK-----------P01
power save level
master adjust only
DOWN INC DEC
ADV/FX/STACK---------P02
power save level
slave adjust only
DOWN INC DEC
SELL SETTINgS
ADV/FX/SELL-----------P01
sell re
volts
DOWN INC DEC
ADV/FX/SELL-----------P01
grid tie
window
DOWN IEEE USER
46
• Press the <DOWN> soft key once to view the power
save level master adjust only screen.
PORT
• The master setting is defaulted at 0. This should not
0
be changed. Press the <DOWN> soft key to view
the power save level slave adjust only screen. Next,
press the <PORT> soft key to view the slave inverter,
PORT
P02 (and P03 if present).
2
• Press the <INC> soft key to change the power save
level for the slave inverters. P02 should be set to 1. If
P03 is present, repeat these steps and set it to 2.
PORT
Two settings in the SELL menu are significant.
• "sell re volts" stands for the voltage level at which the
26.0 vdc
inverter/charger sells renewable energy (RE) back to
the grid. This setting is recommended to be lower
than the settings for your renewable energy source,
but high enough to maintain the battery sufficientliy.
PORT
• The grid tie window has two options displayed on
USER
the screen, but the IEEE setting is not available for
this model of inverter. USER is the only setting that
is available.