This Quick Start Guide does not replace the Operating Instructions
of this product. For complete instructions and safety handling
information, see the Operating Instructions:
Touchscreen Unit:
→
→
DVD: Delivered with the product
Proceq Website: www.proceq.com → Downloads
Scope of Delivery
Profometer 600 (39210001)
Profometer 630 AI / 650 AI (39220001 / 39230001)
Profometer Corrosion (39250001)
Upgrade kit to Profometer Corrosion (39250002)
Upgrade kit to Profometer 600 Cover Meter (39250003)
Profometer Corrosion rod electrode (39250010)
Profometer Corrosion wheel electrode (33001001)
Profometer Corrosion four wheel
electrode (33001004)
A Carrying case
B Profometer touchscreen
C Battery complete
D Power supply incl. cables
E
USB cable
F
DVD with software and documentation
G Documentation
H Activation key
I
Carrying strap complete
J
Probe cable 1.5 m (5 ft)
K Universal probe with ruggedized scan cart
L Chalk
M Interface box
N Cable coil l=25 m (82 ft) with clamp
O Rod electrode with spare parts
P Copper sulphate, 250g
Q Citric acid, 250g
R Electrode cable, 1 lead, l=1.5 m (5 ft)
S Tool kit
T Wheel electrode with cables and spare parts
U Four wheel electrode with cables and spare parts •
© 2018 Proceq SA
Getting Started
1
Battery installation
To install the battery, remove the
protection foil and lift the stand
as shown. Insert the battery and
fasten in place with the screw.
Load battery
The battery must be charged for 8 hours before first use.
Connect through the power supply connection. A Quick
charger is also available (full charging < 5.5 h).
Probes connection
Profometer 6
Connect the universal probe to either of the two sockets
or
on the upper side of the Profometer touchscreen
using the probe cable.
Profometer Corrosion
Mount the interface box on the right side of the
Profometer touchscreen using the attached screws
and
and connect the cable to either of the two sockets
or
on the upper side of the Profometer
touchscreen. Connect the electrode signal cable to socket
and the ground cable to the socket
box. Wheel electrodes: connect the path measurement
cable to socket
• •
• •
•
Start the instrument and enter activation key
2
The following procedure has to be performed at start up
•
in order to upgrade to Profometer 630 AI/650 AI
•
functionalities from a Profometer 600 unit or to unlock
Profometer 600/630 AI/650 AI Cover Meter functionalities
•
• •
on a Profometer Corrosion unit.
• •
1. Press the Power On/Off button to power on the
• •
touchscreen
•
2. Access the System menu, then go to Features and
• • •
Enter activation key
• •
•
→
• •
3. Enter the activation key
•
It is then recommended to check for firmware updates
before using the instrument for the first time (see box
"Profometer Link").
of the interface
of the interface box.
→
→
Main menu
3
On start up, the main menu is displayed. All functions
are accessible directly via the touchscreen.
Return to the previous menu by pressing the back
button or the return icon (arrow) at the top left of the
touchscreen.
Measurement
Select to access either Cover Meter or
Corrosion measuring modes.
Settings
Application specific settings – See Operating
Instructions for details.
Explorer
File manager application for reviewing saved
measurements.
System
Select your preferred interface language, date
and time settings and power saving options.
Information
Refer to the complete Operating Instructions.
Also find important device information.
Power off
Switch off the device.
Profometer Link
Install the Profometer Link software provided on the DVD.
Connect the instrument to a PC using the USB cable provided.
Make sure you are connected to the Internet.
Click on the PQ-Upgrade icon to check for
software updates.
Updates should be performed periodically to take
advantage of Proceq's continuous firmware development.
3