Fig.13
3.- ASSEMBLING THE FRONT AND COLUMNS IN THE L-09 CA MODEL.
1º
Screw on the front with the
columns (the FRONT must be in front
of the columns).
2º Place the boiler and the assembly
(FRONT
–
COLUMNS)
brickwork structure.
3º
Seal the chamber between the
boiler and the front with plaster or
refractory putty (Fig. 14).
4.- SEALING THE HOB
Once the boiler and cooker have been
installed on the brick structure, proceed
to seal the hob to prevent any air from
leaking in around the perimeter that
would affect the air tightness of the
entire assembly. Prepare plaster or
refractory putty and, having removed
on
the
the hob, apply generously around the
entire perimeter.
It is important to perform this sealing
process correctly to achieve maximum
power levels and yield from the cooker.
(Fig. 15).
Fig.14