For ground set up

ATTENTION!
/
The set up must be made frost-free and on level ground.
/
Adhere the supplied rubber feet into the marks on the underside of the tank.
/
Remove the tank cover (release the snap connections on the front, without stretching them too
much).
/
Discharge line connection to the right, modification to the left is possible as follows:
1. Remove the upper left stopper and seal ring.
2. Pull off the discharge line inward.
3. Remove the pump complete with switch from above, turn by 180° and attach it again in the tank
in the intended retainer.
4. Push the discharge connection into the upper left opening.
5. Use the seal ring and stopper to close off the right upper opening.
After installation, place the cover on the tank. The o-ring must be placed evenly in the provided groove in
the tank cover. Push the cover down until all four snap connections engage.
Installation of securing brackets
Keeps the lifting unit safely in place, even in case of flooding.
1. Place the lifting unit in the desired installation location.
2.
Secure unit to the ground with the aid of the brackets (page 40, figure 4).
Connection of discharge pipe
1.
Use a PVC discharge pipe with an outside diameter of 40 mm.
2.
Push the pipe from the outside about 20 mm into the rubber sleeve (use a lubricant if necessary)
and secure it from the inside with the existing hose clamp.
Washing machine/dishwasher connection
1. Remove the stopper from the left or right centre opening.
2.
Insert the hose adapter from the inside.
3.
Push on the washing machine hose and secure with suitable hose clamp.
Other side inlets
1. Remove the stopper of the desired connection.
2.
Push the supply line from the outside approx. 30 mm into the rubber seal (use a lubricant if
necessary).
Vertical inlet: sink connection
1.
Remove the stopper in the tank cover.
2.
Push the siphon down into the corresponding opening.
3.
Connect the siphon loosely to the sink.
4.
Determine the pipe length (allow approx. 20 mm of the pipe to enter the unit), cut to size and
carry out final assembly.
Separate vent line
1. For sensitive applications vent the unit above the roof.
2.
To do so, use the centre side tank opening.
3.
Remove the stopper.
4.
Push the vent line from the outside approx. 30 mm into the rubber seal (use a lubricant if
necessary).
5.
Open the cover of the breather/vent valve in the container cover. Insert the separately supplied