All electrical work must be carried out by qualifi ed electrician and accordance with local supply requirement and associated
regulation.
Method for connecting electric wire
Before connecting the wire, consult the electric power company of jurisdiction.
1. The entire wiring diagram of unit.
a
b
PE
c
d
d.
a. Power supply
e. Remote control
Main switch/fuse
b.
(fi eld supply)
f.
Power supply
c.
wiring for unit
g. Earth
3. Wiring connection to unit
Remove the panel and connect the units power supply wires to terminal block, as shown below.
UAT(Y)(P)60, 80, 100, 120A
Recommended
switch box position
NOTE: While installing the circuit breaker onto the unit, make sure that the screws do not damage the components
(e.g. coil) inside of the unit.
The circuit breaker also can be installed without attaching to the unit.

WIRE CONNECTION

g
f
e
Unit
Connection wiring for
unit & remote controller
UAT(Y)(P)60 only
Terminal block
UAT(Y)(P)250, 300, 360, 420A
2. Remote control wire connection.
UAT(Y)(P)150, 200, 250, 300, 360, 420A
GND
+5
B
A
Connection behind
Top case
Note: For UAT(Y)(P)60, 80, 100, 120A, wire is attached the
remote control. Connect directly to connector 'CN2' on
mainboard.
UAT(Y)(P)150, 200A
Terminal block
Recommended
switch box
position
Terminal block
8
LCD Remote
(Top case)
GND
+5
B
A
Connection at
Mainboard
Connection Wire
(fi eld supply)