5. Service

Service may only be carried out by
authorized and qualified personnel.
Warning: The system must only be
serviced when there is no voltage
or pressure on the system.
1. Turn off the main switch at the
control box (Fig. 1)
2. Open a water outlet to depres-
surise the system.

5.1 Components

5.1.1 Pump / motor

For futher information on Pump/
motor - please see pump manual
from pump supplier.

5.1.2 Control system

Maintenance free
If defective: Call service technician
5.1.3 Flow Switch
Maintenance-free.
If defective, replace the flow switch.
The orientation of the flow switch
has to be done in such way that
the plug/cable end of the switch is
pointing opposite the flow direction.
Flow switch
Plug/Cable
110004660
8
5.1.3.1 Adjustment of flow switch
When the flow switch is replaced/
installed it has to be adjusted.
1. Press "1" on the control panel
to turn on the machine.
2. Turn "rinse/foam" handle on a
satellite to foam position.
3. Activate the spray handle on
the outlet hose of the satellite
so water runs out.
4. Check that the flow switch is
turned the correct way (the
wire must be opposite the flow
direction) (see picture).
5. Remove the white plug/screw
before adjusting (see picture).
6. Adjust the flow to one green
diode lights up (see picture).
7. Close the spray handle again
and check that the red diode
lights up.
8. Remount the white plug/screw.
The flow switch is now adjusted.
The red
diode
Remove
white plug
Flow direction
5.1.4 Non-return valve / inlet side
Maintenance - free.
If defective, replace the non-return
valve.
5.2 Recycling/scrapping
Recycle the wrapping and scrap
the machine according to recom-
mendations from the local authori-
ties.
One green
diode
Adjust settings
110004714
Tabla de contenido

Solución de problemas

loading

Este manual también es adecuado para:

Multi boosterBf16Bf24Bf32Bf40Bf48

Tabla de contenido