The parameter Meter Connection Timeout is the time in
seconds that is required to adjust the nominal PV system
power to 0 W when communication to the energy meter is
interrupted.
To acquire an overview of the current system values, open
the menu Status and select Overview (see figure 21).
Figure 21: LCS-Tool - Overview of current system values
Modbus control
To make this limitation permanent, set the desired
value in the Modbus register 40349.
To disconnect the inverter immediately from the utility
grid while the Limited Export function is running, set
the value "0" in the Modbus register 40348.
For further information on the Modbus interface see
technical information "SUNNY TRIPOWER 60 /
SUNNY HIGHPOWER PEAK1 - SunSpec®
Modbus® Interface" at www.SMA-Solar.com.