Installation - AEG DD9996-B Manual Del Usuario

Ocultar thumbs Ver también para DD9996-B:
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 47
6

INSTALLATION

���
���
As a first step, proceed with the following drawings:
• a vertical line up to the ceiling or up to the upper limit, at the centre of the area in which the hood
is to be fitted;
• a horizontal line at a minimum 960 mm above the cooker top.
• Mark a point (1) on the horizontal line, 292 mm to the right of the vertical reference line.
• Repeat this operation on the other side, checking that the two marks are levelled.
• Mark a reference point (2) as indicated at 200 mm from the vertical reference line and 458 mm
above the cooker top.
• Repeat this operation on the other side, checking that the two marks are levelled.
• Mark a reference point (3) at 743 mm above the cooker top on the vertical reference line.
• Drill at the marked points (1), using a ø 12 mm drill bit.
• Drill at the marked points (2) and (3), using a ø 8 mm drill bit.
• Insert the bracket plugs 11a into the holes (1) and tighten the screws.
• Insert plug 11 into holes (2) and (3).
• Place bracket 7.2.1 on the wall, about 1-2 mm from the ceiling or from the upper limit, aligning
the centre (notch) with the vertical reference line.
• Mark the wall at the centres of the bracket holes.
• Place the bracket 7.2.1 on the wall at X mm below the first bracket (X = height of the upper chim-
ney section), aligning the centre (notch) with the vertical line.
• Mark the wall at the centres of the bracket holes.
• Drill ø 8 mm holes at all the marked centre points.
• Insert the wall plugs 11 in the holes.
• Fix the brackets using the 12a screws (4,2 x 44,4) supplied with the hood.
Wall drilling and bracket fixing
�����
���
��
��
���
��� ���
���
���
EN
Tabla de contenido
loading

Tabla de contenido