VESTEL EVC04 Serie Guia De Instalacion página 31

Tabla de contenido
Idiomas disponibles

Idiomas disponibles

Power Optimizer Meter should be placed just after the main switch of the house as shown in the
figure-20.
Power Optimizer Meter wiring connections can be made according to the information below. See
section 2.6.1- Data Cable Connection
Three Phase
IN
L1
L2
L3
N
22-23: A-B (COM) Modbus connection over RS485 for three phase charging station models. (See
section 2.6.2- STP Connection)
11-12: A-B (COM) Modbus connection over RS485 for single phase charging station models. (See
section 2.6.2- STP Connection)
Related board wiring of Power Optimizer connections can be made as shown below:
IG v7.3.0 2020
Figure-20
OUT
+
L1
+
L2
L3
N
Figure-21
© 2020 Vestel - All rights reserved
Single Phase
IN
L
OUT
L
+
N
+
N
English - 30
Tabla de contenido
loading

Tabla de contenido