Before You Begin (cont.)
Exact location of the end studs will depend on the thickness of the finished wall material.
If installing this unit adjacent to vertical ducts or chases, surround the unit with fire-rated
water-resistant wall material.
When fire-rated wall is specified, stud-opening dimensions are toward the exposed side of the wall
material.
Place the receptor within the installation area prior to completion of the framing.
The basin area requires no additional support when the subfloor is level and square with respect to
the framing. Consider using shims for additional support if the subfloor is uneven.
Consult all applicable instructions for options and accessories before beginning this installation.
Fixture conforms to ANSI Standard Z124.2. All dimensions are nominal. All models meet IAPMO
requirements with the exception of K-9531.

1. Prepare the Site

Ensure that the installation area is clean and free of all debris. If remodeling, remove all finished
wall material to expose the framing and remove all floor coverings to expose the subfloor.
Inspect the flooring at the installation site. Repair as necessary.
Make sure the sub and finished floors are flat and level.