Electrical connection / Commissioning
ATTENTION
Before connecting the device, be sure that the supply voltage agrees with the
value printed on the name plate.
Only have the electrical connection performed by certified electricians.
Ensure that the functional earth (FE) is connected correctly.
Fault-free operation is only guaranteed if the functional earth is connected
properly.
If faults cannot be rectified, take the device out of operation. Protect the
device from accidentally being started.
NOTICE
UL applications
For UL applications, use is only permitted in Class 2 circuits in accordance
with the NEC (National Electric Code).
NOTICE
Protective Extra Low Voltage (PELV)
The device is designed in accordance with safety class III for supply with
PELV (Protective Extra-Low Voltage).
Initial commissioning
The light section sensor is configured via Ethernet with a PC and installed LxSsoft
software before being integrated in the process control.
Connect voltage supply (connection X1) and Ethernet (connection X2).
Switch on operating voltage, green LED must illuminate. The sensor display
shows the alignment aid and the status display.
Set the Ethernet address on the PC (Firewall ports to be opened:
ports 9008 + 5634).
LxS 36 default: IP address 192.168.060.003, net mask 255.255.255.0.
Install configuration software LxSsoft provided on the supplied CD.
Configure light section sensor with the configuration software.