6
Commissioning
6.1
Commissioning the product
PrimoSol® 130-4 is filled via the filling and flushing valves at the flow meter.
PrimoSol® 130-1 is filled via an external filling and flushing unit.
1. Attach a label in the vicinity of the discharge line or to the safety valve with
the following text:
"For safety reasons, liquid must be able to escape via the discharge line
during heating. Do not shut off!"
2. Verify that all connections are tight.
3. Set both ball valves to 45 ° position.
4. Screw hose connectors to the filling and flushing valves.
5. Connect the hoses.
Commissioning
1
2
3
0 ° operation
- Open in direction of flow of solar
liquid
45 ° commissioning, filling, vent-
ing, flushing:
- both ends open (backflow pre-
venter not active)
90 ° maintenance
- closed
PrimoSol® 130
EN
18