A
DJUSTMENT OF THE SAFETY CLUTCH
To be undertaken after disconnecting power supply.
N.B.: These operations must be executed only after the power supply
has been suspended.
1 - Unscrew the unit with a 19 mm wrench (4).
2 - Hold the motor with a 15 mm wrench and turn the screw (3)
clockwise (with the given wrench) if you want more force or unscrew
it if you need less.
3 - After regulating the clutch do not forget to clamp the nut (4) at the
shaft's end.
E
MERGENCY RELEASE
The mod. INDUSTRIAL barrier can be manually operated in a blackout
by inserting the crank into the hole on one side (Pic. 7).
When the crank has been inserted, a switch will depress and disconnect
the line. This prevents the operator from being injured by sudden
unexpected manoeuvres if the electricity supply returns.
M
AINTENANCE
To be undertaken by specialized staff after disconnecting power
supply.
After every 50.000 cycles check the tightness of the boom holding
attachment, and the wear on the mechanical stops.
Grease the bearings of the boom carrier shaft.
L (from 6,5 m to 9,5 m)
A
L
A (mm)
10 m
1205
10,5 m
750
11 m
950
11,5 m
1150
12 m
720
(Pic. 6)
200 mm
B
A
BA10003
SHOCK-ABSORBER
L (from 10 m to 12 m)
E
A
B
B (mm)
C (mm)
3490
610
4390
220
4390
420
4390
420
5290
260
L
A (mm)
B (mm)
6,5 m
1055
7 m
855
7,5 m
1105
8 m
875
8,5 m
1125
9 m
925
9,5 m
725
BA10003
SHOCK-ABSORBER
C
B
D (mm)
E (mm)
1205
5000
750
5250
900
5500
1150
5750
440
6140
N° HANGING RACKS
4390
1 ACG8290 + 1 ACG8291
5290
2 ACG8291
5290
2 ACG8291
6250
2 ACG8290 + 1 ACG8291
6250
2 ACG8290 + 1 ACG8291
7150
1 ACG8290 + 2 ACG8291
8050
3 ACG8291
200 mm
ACG8285
HANGING SUPPORT
D
N° HANGING RACKS
4 ACG8290
2 ACG8290 + 2 ACG8291
2 ACG8290 + 2 ACG8291
2 ACG8290 + 2 ACG8291
4 ACG8291
G
B
6
7
8
9