3.2.
Final installation
3.2.1. Positioning of the tank
The tank must be placed shock-proof and with adequate
equipment into the prepared building pit. After placing the
tank, it must be positioned in the pit in such a way that the
inlet is aligned along the axis of the inlet line. The tank should
be positioned vertically. Make sure the outlet of the separator
is placed 7cm deeper than the inlet. After positioning the
tank, fill the pit layer by layer according to section 3.2.2.
3.2.2. Filling in the building pit
Before filling the tank encasement, the tank shall be filled 1/3 with water, then the
encasement (grounded gravel of maximum grain size 8/16) in layers of a maximum of
30 cm until the tank is filled up to the upper edge. The individual layers must be
compacted well (manual compactor). In order to prevent damage to the tank, the use of
mechanical compacting equipment is not permitted at any time. The encasement must
be at least 500 mm wide.
Attention: In order to be suitable for truck traffic (SLW40), a geotextile must be
horizontally installed around the clearance areas!
Saphir tank series
3. Assembly and Installation