Shutting Down The Unit; Unit Disconnection Process; Disconnecting The Wiring In Push-In Type Terminals - Ingeteam INGECON SUN STORAGE 1Play Manual De Instalacion Y Uso

Ocultar thumbs Ver también para INGECON SUN STORAGE 1Play:
Tabla de contenido
Idiomas disponibles

Idiomas disponibles

Shutting down the unit

20. Shutting down the unit
This section describes the procedure to shut down the unit.
CAUTION
If you wish to work inside the unit, you must carry out these instructions in the order shown here to remove the
power.

20.1. Unit disconnection process

1.
Manually stop the inverter, using the START/STOP option in the display menu.
2.
Remove both the direct voltage (Vdc) and the alternating voltage (Vac) arriving at the unit.
3.
Wait 10 minutes for the internal capacitances to discharge, the hot parts which may cause burns to cool
and the fan blades to stop turning.
4.
Check there is no voltage.
5.
Signal cut-off point (Vac and Vdc) with a sign reading ¨Caution no switching...¨. If necessary, rope off the
work area.

20.2. Disconnecting the wiring in push-in type terminals

INFO
The connection of the storage system, the consumption grid and the auxiliary grid/genset is performed using
push-in type terminals.
Section "7. Connection/disconnection of wiring in push-in type terminals" describes the process for
disconnecting the wiring from this type of terminal.
ABH2013IQM01_C - Installation and Operation Manual
Ingeteam
EN
ES
FR
PT
71
Tabla de contenido

Solución de problemas

loading

Tabla de contenido