Installation Instructions
● Earthing Requirements
1. The air conditioner is classified into the class l appliances, so its earthing must be reliable.
2. The yellow-green line of the air conditioner is the earth line and cannot be used for other
purpose, cut off or fixed by the tapping screw, otherwise it would cause the hazard of the
electric shock.
3. The reliable earth terminal should be provided and the earth wire cannot be connected to
any of the following places.
(1) Running water pipe
(2) Coal gas pipe
(3) Sewage pipe
(4) Other places where the professional personnel think unreliable.
● Noise precautions
1. The air conditioning unit should be installed where ventilation is in good condition,
otherwise the working capability of the unit would be reduced or working noise would be
increased.
2. The air conditioning unit should be installed on the base frame which is stable and secure
uncouth to withstand the weight of the unit, otherwise it would incur vibration and noise.
3. During the installation, a consideration should be taken that the produced hot air or noise
should not affect neighbors or surroundings.
4. Do not stack obstacles near the air outlet of the outdoor unit, otherwise it would reduce
the working capability of the unit or increase the working noise.
5. In the event of the occurrence of abnormal noise, please contact the sales agent as soon
as possible.
6. Accessories for installation
Refer to the packing list for the accessories of the indoor and outdoor units respectively.

Installation of the Outdoor Unit

● Precautions for the installation of the outdoor unit
The following rules should be followed when the installation location is being considered so
as to let the unit run well enough.
1. The discharged air from the outdoor unit won't return back and enough space should be
left for maintenance around the unit.
2. The installation location should be in good condition so that the unit is able to take in and
discharge enough air. Besides, make sure there is no obstacle at the air inlet/outlet of the
unit. If there is, remove it.
3. The unit must be installed where it is secure enough to support the weight of the unit and
capable of reducing to some extent noise and vibration to make sure they do not bother
your neighbors.
4. The designated lifting hole must be used for lifting the unit and protect the unit carefully
during lifting to prevent damaging the mental sheet which would result in rusting in future.