The ground surface on which the inverter is to be placed should be covered with a sponge pad, foam cushion
or the like to prevent the inverter bottom from scratches.
4.3.2 Hoisting Transport
1) Anchor two M10 thread lifting rings to the hangers of the inverter (Fig. 4-7).
2) Lead the sling through the two lifting rings and fasten the tie-down strap.
3) Hoist the inverter, and stop to check for safety when the inverter is 100 mm above the ground (Fig. 4-8).
Continue hoisting the device to the destination after ensuring the safety.
4) Remove the lifting rings and reassemble the sealing screws released before (Fig. 4-7).
WARNING
Keep the inverter balanced throughout the hoisting process and avoid collisions with walls or other objects.
Stop hoisting in the event of severe weather, such as heavy rain, thick fog, or strong wind.
NOTE: The lifting rings and the sling are not within the delivery scope.
4.3.3 Mounting-bracket installation
The procedure to install the ZGR SOLAR STR 250 on Mounting-bracket is as follows:
The dimensions of the assembled mounting-bracket are as follows: