7.1
Instruction
Weld the anchors on the leveller to the reinforcement or the dowels.
Health hazard when welding galvanised components:
Welding galvanised parts produces vapours which can be harmful to health if inhaled. To avoid this, grind the zinc coating
off the parts that are to be welded.
General instruction: The image may differ at detail level.
7.2
Instruction
Before pouring the liquid concrete, the area adjoining the leveller must be shuttered in on site. We recommend covering
the platform with a protective film before pouring the concrete. Pour the liquid concrete. Ensure use of a suitable grade of
concrete, at least C20/25. In the case of a significant casting height, make sure that the side loads caused by pouring and
compacting do not become excessive. Excessive loads could distort the side walls.
General instruction: The image may differ at detail level.
This installation manual must be given to the customer and kept safely during the entire period of use!

7. Final installation actions