6. Assembly
Check that all parts, necessary tools and safety aids are present (e.g. helmet, gloves, safety shoes).
Required tools:
- Rope
- Spirit level
- Ring spanner
Assemble the components following the steps shown in appendix T4
Make all the connections as shown in Annex T3
See the table below for the reference to the annex with the configuration table and configurations per type of rolling tower

Configuration

RS TOWER 34
Configuration table and assemblies
Module 1 (0.75 m platform height) (T4.1 - 4.2)
1. Mount the wheels (part T2.E) and secure with locking pin [T3.1]
2. Open the folding frame (part T2.A), place the platform (part T2.F) on the 2nd rung and secure it [T3.3 - T3.4]
3. Point the wheels outwards, put the brakes on and adjust the base section using a spirit level through the hole pattern in the wheel post
4. Place the horizontal brace (part T2.G) on the upper rung opposite the folding frame [T3.5 - T3.6]
5. Mount the stabilizers (part T2.J) of module A at an angle of 45 degrees.
The scaffold is now ready for use.
Module 1+2 (1.8 m platform height) (T4.1 - 4.5)
1. Mount the wheels (part T2.E) and secure with locking pin [T3.1]
2. Open the folding frame (part T2.A), place the platform (part T2.F) on the 2nd rung and secure it [T3.3 - T3.4]
3. Place a horizontal brace (part T2.G) above the wheels [T3.5 - T3.6]
4. Point the wheels outwards, adjust the base section with a spirit level and put the wheels on the brake [T3.2]
5. Mount the collar tubes (part T2.D). Collar tubes must retain some play [T3.12 - T3.13]
6. Fit and secure the end supports (part T2.C) [T3.9 - T3.11]
7. Mount the large stabilizers (part T2.K) at an angle of 60 degrees [T3.14 - T3.18]
8. Move the platform (part T2.F) to the 6th rung of the folding frame (part T2.A) and secure it [T3.3 - T3.4]
9. Place a diagonal brace (part T2.H) from rung 1 to rung 5 [T3.7 - T3.8]
10. Sit in the platform hatch and position the double guardrail brace (part T2.I) on one side and the 2 horizontal braces (part T2.G) on the
other side from the inside to the outside [T3.5 - T3.6]
11. Mount the side board holders and side boards (part T2.L).
The scaffold is now ready for use.
Module 1+2+3 (3.8 m platform height) (T4.6 – T4.9)
1. Mount the wheels (part T2.E) and secure with locking pin [T3.1]
2. Open the folding frame (part T2.A), place the platform (part T2.F) on the 2nd rung and secure it [T3.3 - T3.4]
3. Place a horizontal brace (part T2.G) above the wheels [T3.5 - T3.6]
4. Point the wheels outwards, adjust the base section with a spirit level and put the wheels on the brake [T3.2]
5. Mount the collar tubes (part T2.D) on the folding frame. Collar tubes must retain some play [T3.12 - T3.13]
6. Mount the collar tubes (part T2.D) on the folding frame (part T2.B). Collar tubes must retain some play [T3.12 - T3.13]
7. Fit the end supports (part T2.B) and secure them [T3.9 - T3.11]
8. Mount the large stabilizers (part T2.K) at an angle of 60 degrees [T3.14 - T3.18]
9. Move the platform (part T2.F) to the 6th rung of the folding frame (part T2.A) and secure it [T3.3 - T3.4]
10. Place a diagonal brace (part T2.H) from rung 1 to rung 5 [T3.7 - T3.8]
11. Sit in the platform hatch and position the double guardrail braces (part T2.I) from the inside out [T3.5 - 3.6]
12. Stand on the platform and place the diagonal braces (part T2.H) from rung 8 to 11 [T3.7 – T3.8]
13. Fit and secure the end supports (part T2.C) [T3.9 - T3.11]
14. Place the platform (part T2.F) on rung 13 and secure it [T3.3 - T3.4]
15. Sit in the platform hatch and position the double guardrail brace (part T2.I) on one side and the 2 horizontal braces (part T2.G) on the
other side from the inside to the outside [T3.5 - T3.6]
16. Mount the side board holders and side boards (part T2.L).
The scaffold is now ready for use.
Attachment
T5
T5
17
www.altrex.com