IMER AP 150 Manual Del Usuario página 16

Tabla de contenido
GB
2.1 PREPARING THE PLACE OF WORK
- The side of the opening to access the load on the floor
must be protected with railings over 1m high and a foot stop.
3. FITTING THE WINCH AND JIB (Fig. 8)
- Caution. While the clamps supporting the winch are
being tightened, take care the winch does not slip down along
the scaffolding pipe as it could crush the installer's hands or
feet.
- Make sure that the clamp screws are fully tightened.
- Make sure that the jib is connected to the scaffolding
with appropriate bracing (Fig.10).
- Do not move the load up or down with the jib and winch
in any position other than the one shown in Fig. 8 so as to
prevent the rope rubbing too much against the walls of the
snub pulleys.
4. CONNECTING TO THE ELECTRIC MAINS
black
white
red
IMER INTERNATIONAL S.p.A.
5. FITTING THE ROPE ON THE JIB (Fig. 9)
5. REGOLATION UP LIMIT SWITCH
6. TESTING
personnel and all the necessary safety precautions must be
taken.
winch.
entire winch installation has been correctly performed.
Fig. 5
16
- Make sure that the split pins are properly inserted.
3
- Caution. This test must be performed by expert, skilled
- Caution: Testing must be performed before using the
- Before commencing testing, carefully check that the
No-load cycle test.
Load test.
GB
1
2
4
Tabla de contenido
loading

Este manual también es adecuado para:

1140497

Tabla de contenido