Installation; Spi-20 And Spi-25 Installation; Tools Required; Fig. 2-2, Channel Lock Plier Locations - EnerSys alpha SPI-20 Manual De Instalación

Tabla de contenido

2.0 Installation

2.1

SPI-20 and SPI-25 Installation

Tools Required

Channel lock pliers
1" torque wrench set to 130 in-lb
Procedure
1. Locate opening for SPI installation (see Fig. 2-1). A knockout is reserved for installation of a secondary SPI
(if required).
2. Remove lid from the enclosure.
3. Hold the SPI in place using channel lock pliers while tightening the nut (see Fig. 2-3 for hardware stack up). Torque to
130 in-lb.
NOTICE:
For proper operation, the SPI must be securely bonded to the enclosure.

Fig. 2-2, Channel Lock Plier Locations

745-997-C0-001 Rev. B (02/2021)
Primary SPI Mounting
Location
Optional
Locations*
(if needed)
*If the SPI is mounted in the location at the top
of the enclosure, the SPI must be mounted
vertically to allow space for other hardware.

Fig. 2-1, SPI Mounting Locations

Attach Channel Lock
Pliers
RF SPI Mounting
Location
Secondary
SPI Mounting
Location
Enclosure Wall

Fig. 2-3, SPI Hardware Stack Up

Nut
Plug