Electrical Connections; Installation; Commissioning; Preparing - EsiWelma Sensigas ESN14 Serie Instrucciones Generales

Detectores de gas para metano y gpl
Tabla de contenido
Idiomas disponibles

Idiomas disponibles

5.

Electrical connections

The installation has to be made in compliance with all the laws in force
Electrical connections have to be made following the diagrams of this instruction. Cables cross section: 1,5 mm²
Max cable length between detector and solenoid valve: 80 m (EV output)
Connect on EV terminals only solenoid valve with electric power not higher than 13W
Detectors must be directly connected to the mains without any switches and being permanently powered up
6.

Installation

Remove the cover, (unscrew the screw on the lower part)
Fasten the body to the wall
Make the electrical connections following the diagrams of these instructions.
Put back the cover on the body. Pay attention to not damage the LEDs
Never touch the sensor or the electronic circuit. Any tampering could be cause of electric shock and
endanger the correct working of the detector.
7.

Commissioning

Detectors do not require any programming or parametrization.
7.1

Preparing

Check that detector chosen is coherent with the gas that has to be detected:
ESN14.G - ESN 16.G - ESN26.G for methane CH4 ESN14.P - ESN 16.P - ESN26.P for liquid petroleum gas LPG
Check that the solenoid valve will be suitable for the desired application
Check that electrical connections are made following the diagrams and the data printed on the back of the detector.
®
EsiWelma
s.r.l.
- 20 -
E192.603