SWB220 Weigh Module » Installation Guide
Options for Securing the Weigh Modules
5
»
BOLT
the weigh module:
Bolt top plate
Tank Leg
Concrete/Foundation
Mounting plate surface must be level to 1/2° or
All weigh modules must be in the same plane within 3mm (1/8").
- OR -
OR
to tank leg
Bolt base plate
Leveling
Adjustment Nut
Shim as
needed
Expansion
Anchor
1mm
(1/16")
100mm (6")
Installation Tips and Precautions:
• Never cut the load cell's cable or extend its length.
• Avoid moisture and dust.
• Ensure voltage stability – use a regulated power supply.
• Avoid overload and shock.
• Ensure good grounding.
LEVEL AND GROUT
the weigh module:
Tank Leg
Bolt top plate
to tank leg
OR
Torque to 136 N-m
(100 ft-lbs)
Bolt base plate
Concrete/Foundation
www.mt.com/ind-downloads-SWB220
- OR -
WELD
the weigh module (bottom plate only):
• Remove load cell from weigh module before welding.
• Ground wire of welder must be as close to the weld
seam as possible to ensure proper grounding.
Torque load cell bolts to 136 N-m (100 ft-lbs).
Contact authorized METTLER TOLEDO technician for
proper removal and re-installation of load cells.
Weld pitch:
3" / 75 mm
Weld size:
0.375" / 9.5 mm fillet
1" / 25 mm long
Tank Leg
Nonshrink
Epoxy Grout
Anchor
Insert
J-Bolt
Contact authorized METTLER TOLEDO service
technician to activate the weigh modules for
startup and calibration.
Contact Information:
www.mt.com/contact
© 2017 Mettler Toledo GmbH, Switzerland
05/2017 | 30372960A
Download Installation Guide:
Installation Guide is available in:
English, Spanish, French
Top plate must
be bolted