2.17.- Ground connection device, ACC/29.
2.18.-Wheels for transport of the tower in vertical position and folded until its location of
work.
3.- Safety precautions.
3.1.- Placing the tower only upon hard and flat surfaces.
3.2.- Check that the legs are inserted in depth and secure by the retaining security
triggers (R).
3.3.- Check that the tower is in vertical position through the bubble's level (F) placed at
the base profile. Adjust, if it is needed, with the plates (Q), turning the handle (H) in the
appropriate sense, always keeping the wheels of the base in touch with the ground as
another supporting point.
3.4.- If it is used out in the open, place the tower in hard ground and secure it against
wind force by means of steel cable braces. The steel cable braces must have 6 mm's
minimal diameter.
3.5.- In case of being necessary the tower will have to get connected to ground
through the connecting device enabled for it, ACC/29.
3.6.- Do not use stairs upon the tower neither lean them in it.
3.7.- Be careful with cables, prominent objects, etc. placed above the tower.
3.8.- Do not stay under the load.
3.9.- Do not move the tower when it is lifted with load.
3.10.- Before using the tower, verify the status of the cable, this must be free of cuts and
fraying. Do not use cables bad conditions.
3.11.- Do not dismount never the winch's handle, neither any element of the winch in
any case
3.12.- It is suggested fixing the winch's handle once you get ready the tower in work
position.
3.13.- The minimum load for the working of the brake without problems is 25 Kg. The
brake will not work without this minimum load.
3.14.- Do not grease neither lubricate the winch's mechanism of brake.
3.15.- Not approved to lift people.
3.16.- For the transport it is necessary to lift down all of the profiles and block them with
the brake (O).
4.- Operating.
4.1.- Place the tower on a flat and firm surface in its site of work