Installation Instructions
INSTALLATION REQUIREMENTS
The SL151i has been designed to be mounted either recessed
into a ceiling, or flush-mounted in a finished ceiling.
Power Requirements
•
230VAC, 50Hz, 2 amps (if NOT installing an
internal outlet for projector).
•
230VAC, 50Hz, 12 amps (if installing an
internal outlet [not provided] for projector).
IMPORTANT ! :
Installation and maintenance of this product
must be completed by a qualified service technician.
Pre-Test Lift before Installation
1.
Carefully inspect the SL151i for any shipping damage. If
any damage is apparent, do NOT continue with the
installation. Instead, contact Chief for further instructions.
2.
Place SL151i upside down on clean surface. (See Figure 1)
Figure 1
3.
Remove and save two screws holding side electrical cover
in place. (See Figure 2)
4.
Remove electrical cover. (See Figure 2)
Electrical
Cover
4
Test inlet
3
Figure 2
5.
Place the jumper wire (H) on the external wiring terminal
contacts labeled 2 and 5, and wire the push button
SL151i top
External
wiring terminal
x 2
assembly (D) to contacts 1 (red) and 6 (black). (See
Figure 3).
Place jumper wire (H) (2 and 5)
Wire push button assembly (D) (1-red, 6-black)
Figure 3
6.
Plug the SL151i test inlet in using the supplied test power
cord (J).
NOTE:
The supplied test power cord (J) may not work in all
countries, and the user may need to supply an
appropriate cord for the country of use.
NOTE:
(See Figure 2) for location of external wiring terminal.
(See Figure 4) for location of internal wiring terminal.
Internal
wiring terminal
Figure 4
Power Requirements and Wiring
The SL151i requires 230VAC, 50 Hz and 2 amps power to
operate.
NOTE:
A 6 ft. long power cord is provided with the mount. This
supplied power cord should be used for testing only,
and not for the permanent installation. (The SL151i will
be hard-wired at installation.)