4 INSTALLATION
4.1 UNIT INSTALLATION
Use the installation guidelines as a reference only.
4.2 GENERAL DUCT WORK INSTALLATION
for more information.
•
•
•
•
•
Install dry air out duct/channel at a high level.
•
•
Allow wet air to disperse freely when exiting the duct.
•
It is recommended to insulate the wet air duct.
•
•
•
4.3 REGENERATION AIR INLET
Free blowing operation require a damper installed to avoid overload. Remove damper when connecting to an air duct.
It is recommended to adjust the damper so that the electric consumption on the ammeter displays the nominal current stated in the technical data.
See heater current in
At delivery, a throttle is installed on regeneration air inlet.
4.4 HUMIDISTAT/ELECTRONIC CONTROLLER INSTALLATION
Install the humidistat/electronic controller away from the dry air out path to avoid false readings.
DC-31 T10, T16 EN.05
.
11
EN
Seibu Giken DST