FIXING THE FIRST RAIL
1. Place the lower rail in position.
2. Fix the rail to the post with 2 screws (s35), through the bracket
holes.
3. Level the rail horizontally. Use timber to help you.
1
2
Make sure the rail is horizontally level, at a 90° angle to the second post.
FIXING THE SECOND POST
1. Attach three brackets to the post using the positioning guide.
2. Place the post in the hole.
3. Fix the post to the rail with 2 screws (s35) through the bracket holes.
4. Add dry or ready mix concrete. Allow concrete to set for 10-15 minutes.
Check that the rail is level and that the post is vertical from both sides.
LEVEL, DOWNWARD SLOPE & UPWARD SLOPE
Position the brackets on the empty side of the post, considering the 3 following options:
option 1
Level
2"-6" (5cm-15cm)
?
GROUND
If the distance is 2"-6" (5-15cm),
place the positioning guide 4" (10cm) from the ground and fix
the brackets with 3 (s18b) screws each.
option 2
Downward slope
2"-6" (5cm-15cm)
?
GROUND
If the distance is more than 6" (15cm),
using 3 (s18b) screws. Fix the second bracket with 3 (s18b) screws using the positioning guide.
INSTALLING A FENCE SECTION
1
2
Make sure the panel goes
Slot the first panel
into the brackets.
into the bottom rail.
INSTALLING A FENCE SECTION
6
7
Assemble the upper rail on
Using screws (s35), fix the
top of the second panel.
upper and middle rails to the brackets.
3
(Take into account the level – downward or upward slope)
2"-6" (5cm-15cm)
GROUND
2"-6" (5cm-15cm)
GROUND
place the lower bracket 2" (5cm) from the ground
3
Assemble the second rail
on top of the panel.
(X2)
SCREW FROM
BOTH SIDES
6
EXTENDING THE POST
The post must be cast at least 12" (30 cm) in the ground. If you have a slope that is
This side up
over 12" (30 cm), you
1
option 3
Upward slope
?
GROUND
In the case of an upward slope, connect the brackets 2" (5cm) up, and/or position the
new post lower while digging a trench for the rail.
Use the positioning guide to make sure that the upper bracket on the left side is
not over the top of the post.
4
Make sure the rail goes
into the brackets.
11
ATTACH POST CAPS
1.
Press caps down on post top.
2. You can secure the caps with silicone.
must extend
the post with timber as shown.
Use 4"/4"/24" (11/11/60 cm timber).
12"-20" (
30-50cm)
Fix with 8 screws.
GROUND
2
3
GROUND
5
Slot the the second
panel into the middle rail.
For fence sections that are less than the standard
6' (182 cm) center-to-center, simply cut the rails
and the fence panels to size, using a power saw.
7
8
o
o
90
90
4
9
GROUND
10
12