DC Alarm Kit
K29-32410 for SL575, SL585, and SL595 Operators
REMOVE THE EXISTING DC ALARM
1. Disconnect power from the operator.
2. Disconnect the wire harness from the main board connections
J1-16 and J1-12 (Figure 1).
NOTE: The J1 terminal block can be removed from the main
board to aid in wiring. If you remove the terminal block, make
sure to replace it securely on the main board.
3. Remove the existing alarm and wire harness (Figure 2).
FIGURE 1
J1 TERMINAL BLOCK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Black wire from alarm
Alarm
AC ALARM
DC ALARM
Removable
connector
Components covered
with heat shrink
Red wire from alarm
Main board
Flange
To reduce the risk of INJURY or DEATH:
• Disconnect all power BEFORE installing or servicing operator.
• See manual prior to servicing regarding maintenance and
required safety testing.
WARNING: This product can expose you to chemicals
including lead, which are known to the State of
California to cause cancer or birth defects or other
reproductive harm. For more information go to
www.P65Warnings.ca.gov.
CARTON INVENTORY
Alarm with wire harness (1)
Extra blue wire stripped on both sides (connects J1-3 to
J1-15) (1)
Wire ties (4)
Flange (41-G0538) (1)
TOOLS NEEDED
Pliers
#2 Phillips Head screwdriver
1/8" flat Phillips Head screwdriver
Diagonal wire cutters
Old alarm
Wire strippers
FIGURE 2
For reference only. Your equipment may look different.
Existing alarm
Operator chassis
Operator chassis
Plastic nut
Regulator
J1 TERMINAL BLOCK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Black wire (-) from alarm
Red wire (+) from alarm
Flange
Plastic nut
Flange
Plastic nut
Main board
Tabla de contenido
loading

Resumen de contenidos para LiftMaster K29-32410

  • Página 1 DC Alarm Kit K29-32410 for SL575, SL585, and SL595 Operators AC ALARM To reduce the risk of INJURY or DEATH: • Disconnect all power BEFORE installing or servicing operator. • See manual prior to servicing regarding maintenance and required safety testing.
  • Página 2 INSTALL THE NEW DC ALARM J1 TERMINAL BLOCK FIGURE 3 1. Insert the provided alarm flange onto the chassis using the mounting holes that held 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 the old alarm.
  • Página 3: Single Phase Wiring Diagram

    SINGLE PHASE WIRING DIAGRAM 115V MOTOR White CONNECTION (SEE NOTE 3) White White 115V ONLY Purple (SL595 Red) Black/Blue To protect against fire and electrocution: • DISCONNECT power BEFORE installing or servicing operator. Black Black Black Black 115V BRAKE White •...
  • Página 4 SINGLE PHASE WIRING DIAGRAM To protect against fire and electrocution: • DISCONNECT power BEFORE installing or servicing operator. • Replace ONLY with fuse of same type and rating. Fuse: 3AG, 3.2A, 120V, SLO-BLO SEE NOTE 5 Black (SL595 Orange) MOTOR SEE NOTE 3 OVERLOAD Yellow...
  • Página 5: Kit De Alarma De Cc

    Kit de alarma de CC K29-32410 para operadores SL575, SL585, y SL595 AC ALARM Para reducir el riesgo de LESIONES GRAVES o la MUERTE: • Desconecte toda la alimentación ANTES de instalar o realizar el mantenimiento del operador. • Consulte el manual antes de realizar el mantenimiento y las pruebas de seguridad necesarias.
  • Página 6: Instalar La Nueva Alarma De Cc

    INSTALAR LA NUEVA ALARMA DE CC BLOQUE DE TERMINALES J1 FIGURA 3 1. Inserte la brida de la alarma suministrada en 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 el chasis utilizando los orificios de montaje que sujetaban la alarma antigua.
  • Página 7: Diagrama De Cableado Monofásico

    DIAGRAMA DE CABLEADO MONOFÁSICO CONEXCIÓN DE Blanco MOTOR DE 115 V (VEA NOTA 3) Blanco Blanco 115V SOLAMENTE Púrpura (SL595 Rojo) Negro/Azul Para proteger contra incendios y electrocución: Negro Negro • DESCONECTAR la alimentación eléctrica ANTES de Blanco Negro SOLENOIDE DE instalar el operador o hacer mantenimiento.
  • Página 8: Cableado De Campo

    DIAGRAMA DE CABLEADO MONOFÁSICO Para proteger contra incendios y electrocución: • DESCONECTAR la alimentación eléctrica ANTES de instalar el operador o hacer mantenimiento. • Reemplace SOLO con fusibles del mismo tipo y capacidad. VEA NOTA 5 Negro (SL595 Naranja) Fusible: 3AG, 3.2A, 120V, SLO-BLO SOBRECARGA VEA NOTA 3 DEL MOTOR...
  • Página 9: Contenu De La Boîte

    Nécessaire d’alarme c.c. K29-32410 pour actionneurs SL575, SL585, et SL595 AC ALARM Pour réduire le risque de BLESSURES GRAVES, voire MORTELLES : • Déconnecter l’alimentation AVANT de procéder à l’installation de l’actionneur ou à une intervention d’entretien sur celui-ci. • Avant les travaux, consulter le manuel pour les instructions d’entretien et d’essai de sécurité.
  • Página 10 INSTALLER L’ALARME C. C. NEUVE BORNIER J1 FIGURE 3 1. Insérer la bride d’alarme fournie dans les 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 orifices de montage du châssis qui retenaient l’ancienne alarme.
  • Página 11 SCHÉMA DE CÂBLAGE MONOPHASÉ CONNEXION DU Blanc MOTEUR (115 V) (VOIR NOTE 3) Blanc Blanc 115V SEULEMENT Mauve (SL595 Rouge) Noir/Bleu Pour protéger contre l’incendie ou l’électrocution : • DÉBRANCHER le courant AVANT d'installer ou de faire Noir Noir Noir Noir SOLÉNOÏDE DE l'entretien de l'actionneur.
  • Página 12 • Retirez le fil vert de la borne R4 du bloc radio et raccordez-le à la position 6 du bornier TB1. • Déplacez le fil brun de la position 6 du bornier TB1 (venant du bloc radio R4) à la position 1 du bornier TB1. © 2016, LiftMaster All Rights Reserved Tous droits réservés...

Tabla de contenido