3.6.18. Calibrating the ORP probe
1) Open the ORP 470 mV calibration solution.
2) Turn off the filtration (and therefore the electronics unit).
3) If the probe is already installed :
a) Remove the probe from the probe holder, without disconnecting it.
b) Remove the probe holder nut and replace it with the stopper supplied.
If the probe is not already installed :
Connect the probe to the electronics unit.
4) Turn on the electronics unit.
5) Go to the «
Electrolysis - ORP Calibration
6) Navigate through the menus following the instructions below :
Electrolysis
ORP Calibration
OK
ORP Calibration
Solution
470 mV
OK
ORP Calibration
In Progress
(Wait a few seconds)
ORP Calibration
Success
or
ORP Calibration
Failed
3.6.19. Activation/deactivation of pH regulation
Menu
pH Regulation
Mode
XXX
3.6.20. Manual injection
Menu
• Priming
peristaltic
and filling of semi-
rigid pipes.
• pH
pH Regulation
Manual Injection
injection.
• Means of checking
the
operation of the
peristaltic pump.
» menu.
→ Insert the probe into the ORP calibration solution, then wait a few minutes.
→ Do not touch the probe.
→ a) Rinse the probe under running water, then leave to drip-dry it without wiping it.
b) Install the probe into the probe holder.
→ Carry out the navigation again with the above instructions, several times if necessary.
If calibration still fails, replace the probe and carry out another calibration.
Possible settings
• ON
• OFF
Functions
Possible settings
of
the
pump
From 30 seconds
to 10 minutes, in
corrector
increments of 30
seconds.
correct
Default setting
Default setting
• To start injecting :
Confirm the duration setting.
(The peristaltic pump is running,
and a timer countdown is
displayed in real time.)
1 min
• To take a break, and to restart
the injection :
Press on OK.
• To stop the injection :
Press on
ON
Instructions
.
12