TEF 2880 NAVIGATION LIGHT -
INSTALLATION
Electrical termination
Only qualified electrical personnel may install and start up the QPD components.
For correct electrical termination please follow the Phoenix user manual, Appendix 1 in the end of this user manual.
Below is an excerpt of the Phoenix user manual describing the main points of the procedure.
Please note that the dust caps mounted on lights connector sockets are not IP rated and will not protect against water
intrusion.
Cable termination
• Cable diameter: Ø9-16 mm.
Part # 2880***0* delivered as standard with terminal nut for Ø9-16 mm cable.
Wire cross section: 1.0 mm
Wire diameter incl. insulation: 2,0 mm to 3,80mm.
Connections
1. Strip approx. 60 mm off the cable.
2. Loop the PE conductor around the live conductors
(1). As a result, the PE conductor will be pulled out of
the terminal block last if strong tension is exerted on
the cable.
3. Insert the cable into the terminal nut.
4. Fix the wires in the conductor support of the splice
body (2).
5. Cut off the wires with a diagonal cutter flush on the
splice body (3).
6. When connecting the terminal nut to the light
connector socket, make sure that their markings are
aligned.
7. Screw the terminal nut together with the light
connector socket (4). For this, we recommend using
either the socket wrench, a wrench, or a pliers.
Screw the terminal nut as far as it will go, or with the
specified torque. It must not be possible to unscrew
the terminal nut again by hand.
8. Seal off any non-allocated connections using a
protective cap.
Page 8
to 2.5 mm
.
2
2
INSTALLATION AND USER MANUAL
1
3
Photos courtesy of Phoenix Contact GmbH.
Ground bonding screw
The navigation lights are equipped with an external M5
ground bonding screw. Connect to ground where na-
tional or company regulations require it.
2
4