e
quIPotentIal connectIon
The whirlpool tub must be connected to the
equipotential system of the building by a cable
with a section of 2.5 mm
performed by means of the terminal marked
, located on the metallic support (Fig.3).
84 84
TT0283385_02_SOFT_CMYK.indd 84
2
. to 6 mm
2
. Connection is
Fig.3
o
PeratIon check
After carrying out electrical and hydraulic con-
nections and prior to fastening the tub in place,
perform an operation check by following the
instructions below:
Move the tub far enough away from the wall
to be able to see all hydraulic fixtures.
- Close the contact of the omnipolar switch for
the electrical system by placing the lever in
position I.
- Check that the LED of the O/I button comes on
in the colour as specified in the chapter on the
operation of the whirlpool systems.
- Fill the tub up to a level which is 5 cm above
the nozzle;
- Check that there are no water leaks from the
tube system.
- Check the colours of the various LED's as shown
in the chapter on the operation of the whirlpool
systems.
- Check proper operation of jets and of the water/
air mixture.
- Check once again that there are no leaks from
the tube system.
- Switch the system on and back off as a test at
least twice.
5-07-2010 16:34:11