1
INSTALLING A POD
Refer to Installing the POD
illustration above.
1. Remove the POD cover
• Remove the screws attaching
the port cover panel and
retain them for reassembly.
• Remove the POD port cover
and set aside.
2. Align the POD connectors
• Align the connectors on the
POD with those inside the
port, making sure that the
colors match.
• Connect them and make
sure that the connectors are
fully seated.
3. Insert the POD in the port
• Tilt the top away from the
port and insert the lower
edge into the slot.
• Press the top toward the MBC,
and press the POD into place.
• Secure the POD with the
screws removed from the
port cover plate.
To contact Vertiv Technical Support: visit www.VertivCo.com
© 2019 Vertiv Co. All rights reserved. Vertiv and the Vertiv logo are trademarks or registered trademarks of Vertiv Co. All other names and logos referred to are trade names,
trademarks or registered trademarks of their respective owners. While every precaution has been taken to ensure accuracy and completeness herein, Vertiv Co. assumes no
responsibility, and disclaims all liability, for damages resulting from use of this information or for any errors or omissions. Specifications are subject to change without notice.
4
590-2144-665A/SL-26256QS_REV2
2
Cover
screws
connectors
Cover
UPS Operation and Display Panel
Escape
Up
Down
Enter
POWERING THE MBC
1. If the two plastic bezels are
attached, pull both ends with
equal force to remove them.
2. On the front panel, verify that
the maintenance-bypass
breaker (MBB) is Off (open) and
that the breaker interlock is
secured in place.
3. In the external panel, close the
feeder breakers to provide main
input and, for a dual-input
system, bypass input.
4. On the front of MBC, close the
rectifier-input breaker (RIB),
bypass-isolation breaker (BIB)
POD
PP75
3
and maintenance-isolation
breaker (MIB).
5. If a POD is installed, verify that
the distribution breakers on the
POD are closed.
6. Power-on the UPS using the
Operation and Display Panel by
pressing the power button until
the confirmation dialog appears.
Use the Up/Down arrows to
select "YES", then press Enter.
The connected equipment is
supplied protected power from
the UPS.
7. Reinstall the bezels on the front
of the MBC.
Run
Alarm
Display
Power