Leak Test Of Propane Liquid Gas Fittings Pursuant To 1 - Rothenberger ROTEST GW 150/4 Instrucciones De Uso

Ocultar thumbs Ver también para ROTEST GW 150/4:
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 32
Insert the open end of the connecting hose (6) to the valve on the test plug.
Assemble tube element system as follows:
-
while carefully turning insert tube element (8) with scale 40 - 60 mbar into fixed tube
element (7).
-
while carefully turning insert tube element / end piece (9) with scale 110 mbar into tube
element (8).
while carefully turning insert additional tube element (10) into tube element / end piece
-
(9) with scale 150 mbar
Seal off the hose end of the bellow (12) by sliding end over connecting valve C on the
water tank.
Open connecting valves B, C and D
Use bellow (12) to load a pressure pursuant to 1* into the test system.
Close connecting valve C to avoid a loss in pressure.
Wait 10-60 minutes (dependent on pipe volume) for loaded air and water temperatures to
equalize.
Prolong 10-60 minute period of temperature equalization if temperatures fluctuate
greatly. The equalization period can last up to two hours!
Carry out the test over a period prescribed by 1*. Over this period the pressure indicated must
not drop.
5.1.2

Leak test of propane liquid gas fittings pursuant to 1*

Complete test as follows:
Close all cut-off valves on your ROTEST GW 150/4.
Insert connecting hose (6) to connecting valve B. An auditable sound is heard when hose
and valve nipple are properly locked.
Insert an appropriate test plug into the open end of the pipe and seal off end by turning the
wing nut until the pipe is sealed tight.
Insert the open end of the connecting hose (6) to the valve on the test plug.
Assemble tube element system as follows:
while carefully turning insert tube element (8) with scale 40 - 60 mbar into fixed tube
-
element (7).
-
while carefully turning insert tube element / end piece (9) with scale 110 mbar into tube
element (8).
-
while carefully turning insert additional tube element (10) into tube element / end piece
(9) with scale 150 mbar.
Seal off the hose end of the bellow (12) by sliding end over connecting valve C on the
water tank.
Open connecting valves B, C and D.
Use bellow (12) to load a pressure pursuant to 1* into the test system.
Close connecting valve C to avoid a loss in pressure.
Wait 10-60 minutes (dependent on pipe volume) for loaded air and water temperatures to
equalize.
Prolong 10-60 minute period of temperature equalization if temperatures
fluctuate greatly. The equalization period can last up to two hours!
Carry out the test over a period prescribed by 1*. Over this period the pressure indicated must
not drop.
1* Statutory regulations in the country of use or the respective manufacturer and facility instructions and guidelines
16
ENGLISH
Tabla de contenido
loading

Este manual también es adecuado para:

6.10396.10406.1045

Tabla de contenido