Light Assembly Installation
1.
Switch off main electrical switch or circuit breaker, and the switch which
operates the light.
2.
Route light cable through conduit to Junction Box, leaving at least 4 feet (1.2 m)
of cord coiled inside of the niche. This allows the light to be serviced on the deck
while the pool/spa is filled with water.
3.
Cut the cable at the Junction Box, leaving at least 6-inches (15.3 cm) of cord to
make connections.
GFCI Circuit
Breaker and
Power Source
Rigid
Conduit
#8 AWG Bonding Connector
(located on outside of niche)
DETAIL
Junction Box must have a water tight bushing
GFCI Circuit
Breaker and
Power Source
Rigid
Conduit
#6 AWG Bonding Connector
(located on outside of niche)
DETAIL
4 ft (1.2 m) minimum
4 in (10.2 cm) minimum
Pilot Screw
at 12 o'clock
Tie offs to
rebar
FIGURE 4 (US Installs)
3 m (9.8 ft) minimum
Pilot Screw
at 12 o'clock
Tie offs to
rebar
FIGURE 5 (Canadian Installs)
INTELLIBRITE
Architectural Series Pool/Spa Light Installation and User's Guide
®
8 in (20.3 cm)
Junction Box or Low Voltage
Transformer, to the max water level.
18 in (42.7 cm)
minimum to top of lens
11.5 in (29.2 cm) minimum
Concrete must be cut around
niche to allow for compacted
plaster seal.
Wrap 4 ft (1.2 m) of light
cable around fixture
16 in
(40.6 cm)
60 cm (23.6 in)
minimum to top of lens
29.2 cm (11.5 in) minimum
Concrete must be cut around
niche to allow for compacted
plaster seal.
Wrap 1.2 m (4 ft) of light
cable around fixture
40.6 cm
(16 in)