4 Installation and connection

4.1 Installation site requirements
Sample gas probes are intended for flange mounting.
• Installation site and installation position are determined
based on requirements specific to the application.
• If necessary, the connection piece should be slightly tilted
toward the centre of the channel.
• The installation site should be protected from the
weather.
• In addition, adequate and safe access for installation and
future maintenance work should be provided. Particularly
follow the uninstalled size of the probe tube!
If the probe is transported to the installation site in pieces, it
will first need to be assembled.
4.2 Installation
DANGER
Danger to life and explosion during installation and
maintenance
The unit must not be worked on (assembly, installation,
maintenance) in explosive atmospheres.
DANGER
Explosion hazard
When used in explosive areas
Flammable gasses and dust could ignite or explode.
Never operate the gas probe outside the specifications. Ex-
tracting gases or gas mixtures which are also explosive in the
absence of air is prohibited.
DANGER
Explosion hazard due to ignition of dust
When using the device in a dusty environment, routinely
clean dust from all components.
The ignition temperature resp. smouldering temperature of
flammable dusts resp. dust layers present must be consider-
ably higher than the maximum surface temperature of the
device (observe applicable standards and statutory regula-
tions).
If possible, take the electrical components which must be
opened for repair to a dust-free room. If unable to do so, pre-
vent dust from entering the housing.
DANGER
Explosion hazard due to flame propagation
Severe injuries and damage to the system
If the process holds a risk of flame propagation, install a
flame arrestor.
4.3 Installing the sampling tube (optional)
The sampling tube, if necessary with the fitting extension,
must be screwed in. The probe is then attached to the mating
flange using the included seal and nuts.
10
Bühler Technologies GmbH
4.4 Installing the outlet filter
NOTICE
The outlet filter and the O-ring for the handle must be inser-
ted prior to first startup.
Operating without outlet filter prohibited!
O-ring handle
4.5 Installing the Inlet Filter (Optional)
The inlet filter, if necessary with matching extension, must be
screwed in. The probe is then attached to the mating flange
using the included seals and screws.
4.6 Insulation
On heated probes completely insulate any exposed flange
areas and, if applicable, the connection piece to absolutely
prevent thermal bridges. The insulating material must meet
the application requirements and be weatherproof.
4.7 Connecting the Gas Line
The sample gas line must be carefully and properly connected
using a suitable fitting.
This table provides an overview of the sample gas probe con-
nections:
Probe
GAS 222
Connecting
DN65/PN6/
1)
2)
flange
DN3"-150
Sample gas
G3/4
inlet
Sample gas
NPT 1/4
outlet
Blowback
G3/8
connection
Test gas con-
Tube Ø6 mm
1)
2)
nection
Tube Ø1/4
Filling port
Condensate
Bypass
Control air
Tab. 1: Gas Probe Connections (Varies by Model)
1)
Varies by version.
2)
Only GAS 222.xx ANSI and GAS 222.xx AMEX
Attach an O-ring suitable for the
expected ambient temperature
to the handle.
Attach the outlet filter to the
handle. Then carefully insert the
handle with filter in the gas
probe and turn 90° to secure.
Verify the handle is seated cor-
rectly. When seated correctly it
locks onto the filter housing.
Reservoir
Ball valve
Control
PAV01
pneumatic
valve
drive
3/2-way
solenoid
valve
NPT 1/4
G1/2
NPT 1/4
G1/8
G1/4
NPT 1/4
BX460050 ◦ 01/2020
Tabla de contenido
loading

Tabla de contenido