Installation
Fantasia Line is provided with ceiling hose, lead, 2 meters' flexible hose D160 mm.
NB. Electric installations must be carried out by an authorized electrician.
Before installing Fantasia Line carry out the following preparations:
Establish an outlet to the open either through the ceiling or the wall.
(One might use the ceiling hose to mark the hole)
Ceiling Hose
After correct marking and establishment of the outlet hole the ceiling hose is fastened to the ceiling with
4 rawlplugs and 4 screws.
Electric Connection (230 V)
The lead is internally led through the chimney to an electric connection.
For models with internal engine there is one cable marked with 230 V.
For models without engines there are two cables:
One marked with 230 V
One marked engine. (Here an extension lead is installed which should be used for the connection to the
plug from the external engine).
Installation of Flexible Hose
The flexible hose (D160 mm) is led through a hole in the ceiling or the wall and is installed on the roof
cowl or the wall flange.
If you have chosen an external engine the installation of flexible hose (D160 mm) will be for induction
flange on roof ventilator, ceiling ventilator or on external wall ventilator.
Installation Height
The installation height is individual, but it is recommended to have 50-60 cm above an
electric stove and 70 cm above a gas cooker. (Measured from the edge of the table to the filter of the
canopy).
Chimney Installation
If the chimney is too long it must be shortened on top with a hacksaw or an angle grinder.
The chimney/canopy is subsequently fastened to the ceiling hose with 4 screws.
Wall model must also be fastened on the wall (below).
NB The bottom plate must be dismounted before.
NB Remember that the flexible hose/pipe and lead must be led through the chimney.
Technical Data Ronda:
Connection voltage
Pre-securing
Carrying capacity
Working temperature
230V AC+6-10%, 50 Hz
max. 13A
4A total and maximum CKB 2000
-10 -+50˚C