9 SPOUT INSTALLATION
Apply PTFE plumbers tape on both ends of Pipe Nipple (9A) (not included).
Screw Pipe Nipple (9A) into the elbow inside the wall and tighten with pipe
wrench. The Pipe Nipple (9A) is to project 3
Screw Tub Spout (9B) onto Pipe Nipple (9A) and tighten until Spout is properly
positioned and flush to the finished wall.
10 UNIT START UP
Turn on hot and cold water supplies, and check all connections for leaks.
11
11A
CLOSED
11 VALVE FUNCTION
By rotating the Handle (11A) slightly counterclockwise, the valve will be fully
activated to the "COLD" position. The water temperature can be increased by
continuing to rotate the Handle (11A) in a counterclockwise direction.
9A
/
" to 4 "
3
7
8
⅞
" to 4" from the finished wall.
FULL HOT
OPEN
FULL COLD
ENGLISH
12
12C
BUTTON DOWN FOR TUB
BUTTON UP FOR SHOWER
12B
12 FINAL FLUSHING
For final flushing, turn valve on and allow water to run through the Tub Spout
(12A) for several minutes. Pull Spout Knob (12B) up to allow water to run through
Shower Arm (12C). Allow water to run for several minutes untill all foreign mater
clears the line.
13
13 SHOWER HEAD INSTALLATION
Thread Shower Head (13A) onto Shower Arm (13B), placing Washer (13C)
in between.)
Make sure Shower Head (13A) is securely tightened to Shower Arm (13B).